Net metering · Private distribution utility

AEC net metering: how to apply

Angeles Electric Corporation. AEC hasn’t published its own net-metering checklist online, so here are the national rules that apply and how to contact AEC.

Checked October 27, 2026. Rules and fees change; confirm with AEC before you apply.

At a glance

How to apply
Contact AEC and ask for its net-metering desk.
ERC fee
—
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)

What we found

  • We could not find a published net-metering process for Angeles Electric. Its website (aec.com.ph) could not be opened on 27 October 2026 because of a security certificate error.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Rules AEC must follow

AEC net metering FAQs

How long does AEC take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.