Net metering · Electric cooperative
PELCO II net metering: how to apply
Pampanga II Electric Cooperative. Here’s PELCO II’s net-metering process, documents and fees, from its own published guide.
Checked October 27, 2026. Rules and fees change; confirm with PELCO II before you apply.
At a glance
- How to apply
- Submit a letter of intent addressed to the General Manager with the listed documents. PELCO II provides the application form and the ERC COC form.
- ERC fee
- ₱1,500.00
- Meter replacement
- Capped at ₱3,000 for residential customers (ERC)
- Processing time
- 20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)
Steps to apply with PELCO II
- 1 Letter of intent Write to the General Manager, Mr. Amador T. Guevarra. Include your account name, account number, address, contact number, email address and signature.
- 2 Submit documents Submit the documents in the requirements list. All documents must carry the same name as your PELCO II account.
- 3 Pay the inspection fee Pay the inspection fee.
- 4 Inspection PELCO II inspects your installation. It may ask for more documents during the application or inspection.
Requirements PELCO II lists
- Letter of intent addressed to the General Manager
- Electrical plan signed and sealed by a Professional Electrical Engineer (schedule of loads and single line diagram with the solar panels)
- Net-metering application form (provided by PELCO II)
- ERC Certificate of Compliance (COC) form (provided by PELCO II)
- Electrical permit from the Municipal Engineering Office (original or certified true copy)
- Certificate of Final Electrical Inspection from the Municipal Engineering Office (original)
- Brochure of materials used
- Photocopy of your latest PELCO II bill
- Photocopy of a valid ID with three specimen signatures
The ERC’s September 2025 advisory says utilities may only require the application form, the CFEI from your LGU, the amended net-metering agreement and the ERC fee. If an item above isn’t on that list, ask PELCO II whether it’s still required.
Fees
| Fee | Amount |
|---|---|
| Inspection fee (per PELCO II's 31 July 2026 post) | ₱1,680.00 |
| ERC filing fee (per PELCO II's FAQ page) | ₱1,500.00 |
LGU permit fees (electrical permit, CFEI) are separate and vary by city or municipality.
How long it takes
- 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
- 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
- Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)
Good to know
- Open to member-consumer-owners with renewable systems (solar, wind, biomass or biogas) of up to 100 kW. PELCO II credits exports at its blended generation cost, excluding other generation adjustments.
- PELCO II's two pages differ. The 31 July 2026 post lists a ₱1,680.00 inspection fee and an electrical permit. The undated FAQ page lists a ₱1,500.00 ERC filing fee and no electrical permit or inspection fee. Ask PELCO II for the current list and total fees.
- The ERC's 22 September 2025 advisory limits what utilities may require to an application form, the CFEI, the amended agreement and the COC fee, and bars items such as solar equipment catalogs. Ask PELCO II whether the brochure and other extra items are still needed.
Contact PELCO II
PELCO II Hotline (045) 900-0423 local 153.
PELCO II net metering FAQs
How much does net metering cost at PELCO II?
How long does PELCO II take to process net metering?
What documents does PELCO II ask for?
Sources
- Thinking of installing a solar power system for your home or business? Here's what you need to know about net-metering — Pampanga II Electric Cooperative (accessed October 27, 2026)
- Frequently Asked Questions — Pampanga II Electric Cooperative (accessed October 27, 2026)
- Advisory to On-Grid Distribution Utilities in Compliance with the Net-Metering Program (22 September 2025) — Energy Regulatory Commission (copy hosted by BATELEC II) (accessed October 27, 2026)