Skip to main content
SmartEnergyPH

Net metering · Electric cooperative

BATELEC II net metering: how to apply

Batangas II Electric Cooperative. Here’s BATELEC II’s net-metering process, documents and fees, from its own published guide.

Checked October 27, 2026. Rules and fees change; confirm with BATELEC II before you apply.

At a glance

How to apply
Download the Net Metering Application Form from BATELEC II's website. BATELEC II's dedicated net-metering application page was still under development on 27 October 2026.
ERC fee
Not listed by the utility
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)
BATELEC II’s net-metering page

Requirements BATELEC II lists

  • BATELEC II Net Metering Application Form. It asks for applicant and account details, system capacity and type, transformer and inverter details, a single line diagram, and a site plan sketch.

The ERC’s September 2025 advisory says utilities may only require the application form, the CFEI from your LGU, the amended net-metering agreement and the ERC fee. If an item above isn’t on that list, ask BATELEC II whether it’s still required.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Good to know

  • BATELEC II publishes its application form and a copy of the ERC's 22 September 2025 advisory, but not its own step-by-step process or fees.
  • The ERC advisory says a utility's required documents are limited to an application form, the CFEI from the LGU, the amended net-metering agreement and the COC application fee.

Contact BATELEC II

(043) 756-6337 / (043) 756-1424; corporate@batelec2.ph; Antipolo del Norte, Lipa City, Batangas.

BATELEC II net metering FAQs

How long does BATELEC II take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.
What documents does BATELEC II ask for?
BATELEC II lists 1 items, including batelec ii net metering application form. it asks for applicant and account details, system capacity and type, transformer and inverter details, a single line diagram, and a site plan sketch. The ERC’s September 2025 advisory limits required documents to the application form, the CFEI, the amended agreement and the ERC fee, so ask BATELEC II which items are still needed.

Sources