Visayan Electric net metering: how to apply

Visayan Electric Company. Here’s Visayan Electric’s net-metering process, documents and fees, from its own published guide.

Checked October 27, 2026. Rules and fees change; confirm with Visayan Electric before you apply.

At a glance

How to apply
Fill in Visayan Electric's online Net Metering Application Form (a Google Form linked from its net-metering page), then submit the listed documents. For help, visit any Visayan Electric Customer Service Center.
ERC fee
Not listed by the utility
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)
Visayan Electric’s net-metering page

Steps to apply with Visayan Electric

  1. 1 Submit your application Send the application form and the documents in the requirements list.
  2. 2 Evaluation by Visayan Electric Visayan Electric runs a Distribution Impact Study at no cost, checks your renewable energy system and service entrance, and reviews your billing clearance and bill deposit. The LGU electrical permit (CFEI) is submitted at this stage.
  3. 3 Approval and final steps Pay the relevant fees and update your bill deposit if needed. Sign the Amended Net Metering Agreement. Visayan Electric does a final inspection, installs the meters, and energizes and commissions the system.

Requirements Visayan Electric lists

  • Net Metering Application Form (online Google Form)
  • Qualified Entity (QE) Certificate of Compliance (COC) Form
  • QE COC Application Form (Solar)
  • Plant Parameters and Load Logger Authorization
  • Net Metering Agreement: Affidavit and Waiver, NMA with REC, or NMA without REC
  • Signed and sealed electrical plans
  • Equipment technical specifications
  • Valid IDs and proof of ownership
  • LGU electrical permit / Certificate of Final Electrical Inspection (CFEI)

The ERC’s September 2025 advisory says utilities may only require the application form, the CFEI from your LGU, the amended net-metering agreement and the ERC fee. If an item above isn’t on that list, ask Visayan Electric whether it’s still required.

Fees

FeeAmount
Distribution Impact StudyFree

LGU permit fees (electrical permit, CFEI) are separate and vary by city or municipality.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Good to know

  • Visayan Electric says its program follows the ERC's Amended Net Metering Rules of 2025 and links to a copy on its website.
  • The page says to "pay relevant fees and update bill deposit (if needed)" but does not list peso amounts.
  • The page mentions installing a bi-directional and REC meter, but it also offers an "NMA without REC" form and an Affidavit and Waiver. Under the 2025 amended rules the REC meter is optional.
  • Visayan Electric posted that it supports the ERC's new net-metering guidelines (post dated 30 September 2025). The ERC's 22 September 2025 advisory limits what utilities may require to an application form, the CFEI, the amended agreement and the COC fee, and bars items such as bills of materials or equipment catalogs. Ask Visayan Electric which items on its list are still required.

Contact Visayan Electric

Hotline (032) 230-8326; mobile 0919-056-VECO (8326); email info@visayanelectric.com; VECO Engineering Office, J. Panis Street, Banilad, Cebu City.

Visayan Electric net metering FAQs

How much does net metering cost at Visayan Electric?
Visayan Electric lists: Distribution Impact Study — Free. For residential customers, the meter replacement charge is capped at ₱3,000.
How long does Visayan Electric take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.
What documents does Visayan Electric ask for?
Visayan Electric lists 9 items, including net metering application form (online google form) and qualified entity (qe) certificate of compliance (coc) form. The ERC’s September 2025 advisory limits required documents to the application form, the CFEI, the amended agreement and the ERC fee, so ask Visayan Electric which items are still needed.