Cotabato Light net metering: how to apply

Cotabato Light and Power Company. Cotabato Light hasn’t published its own net-metering checklist online, so here are the national rules that apply and how to contact Cotabato Light.

Checked October 27, 2026. Rules and fees change; confirm with Cotabato Light before you apply.

At a glance

How to apply
Contact Cotabato Light and ask for its net-metering desk.
ERC fee
—
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)

What we found

  • We could not find a step-by-step net-metering process or checklist on Cotabato Light's website.
  • Cotabato Light's 1 December 2025 post "Net-Metering Just Got Easier!" restates the ERC changes: fewer documents, no notarized agreements, free testing and commissioning, a ₱3,000 cap on the bi-directional meter fee, and rebates that start right after testing.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Rules Cotabato Light must follow

Contact Cotabato Light

(63-64) 520-2572; 0919-056-2572; cotabatolight@aboitizpower.com; Sinsuat Avenue, Rosary Heights 1, Cotabato City.

Cotabato Light net metering FAQs

How long does Cotabato Light take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.

Sources