MORE Power net metering: how to apply

MORE Electric and Power Corporation. MORE Power hasn’t published its own net-metering checklist online, so here are the national rules that apply and how to contact MORE Power.

Checked October 27, 2026. Rules and fees change; confirm with MORE Power before you apply.

At a glance

How to apply
Contact MORE Power and ask for its net-metering desk.
ERC fee
—
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)

What we found

  • We could not find a net-metering procedure on MORE Power's website. Its homepage mentions net metering only in the Lifeline Rate section.
  • News reports from November 2024 say the ERC approved MORE Power's request to consolidate net-metering and DER Certificate of Compliance applications at its customer care office in Iloilo City, with ERC representatives on a monthly schedule there. Ask MORE Power for its current checklist and fees.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Rules MORE Power must follow

Contact MORE Power

Hotlines 033 526-6673 and 09175576130; email customercare@morepower.ph.

MORE Power net metering FAQs

How long does MORE Power take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.