Negros Power net metering: how to apply

Negros Electric and Power Corporation. Negros Power hasn’t published its own net-metering checklist online, so here are the national rules that apply and how to contact Negros Power.

Checked October 27, 2026. Rules and fees change; confirm with Negros Power before you apply.

At a glance

How to apply
Contact Negros Power and ask for its net-metering desk.
ERC fee
—
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)

What we found

  • We could not find a net-metering page on Negros Power's website.
  • News reports from November 2024 say Negros Power's net-metering Certificate of Compliance applications are among those the ERC processes through MORE Power's one-stop arrangement in Iloilo City.
  • SmartEnergyPH's rate data lists this utility under the code CENECO/NEPC.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Rules Negros Power must follow

Contact Negros Power

034 705-6372 (034 705-NEPC); 09176837250; customercare@negrospower.ph; The Row, Lacson Street, Barangay Bata, Bacolod City.

Negros Power net metering FAQs

How long does Negros Power take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.