Net metering · Private distribution utility
Negros Power net metering: how to apply
Negros Electric and Power Corporation. Negros Power hasn’t published its own net-metering checklist online, so here are the national rules that apply and how to contact Negros Power.
Checked October 27, 2026. Rules and fees change; confirm with Negros Power before you apply.
At a glance
- How to apply
- Contact Negros Power and ask for its net-metering desk.
- ERC fee
- —
- Meter replacement
- Capped at ₱3,000 for residential customers (ERC)
- Processing time
- 20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)
What we found
- We could not find a net-metering page on Negros Power's website.
- News reports from November 2024 say Negros Power's net-metering Certificate of Compliance applications are among those the ERC processes through MORE Power's one-stop arrangement in Iloilo City.
- SmartEnergyPH's rate data lists this utility under the code CENECO/NEPC.
How long it takes
- 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
- 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
- Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)
Rules Negros Power must follow
- Only four requirements. Utilities may only ask for the application form, the Certificate of Final Electrical Inspection (CFEI) from your city or municipality, the amended net-metering agreement, and the ERC Certificate of Compliance fee. They may not ask for a bill of materials or equipment catalogs. (Energy Regulatory Commission (copy published by BATELEC II))
- No notarization needed. Having the net-metering agreement notarized is not mandatory. (Energy Regulatory Commission (copy published by BATELEC II))
- Meter fee capped at ₱3,000. For residential customers, the charge for replacing your meter with a bi-directional meter is capped at ₱3,000. (Energy Regulatory Commission (copy published by BATELEC II))
- Free testing and commissioning. Testing and commissioning are free and must happen within the utility’s processing period. (Energy Regulatory Commission (copy published by BATELEC II))
- Up to 100 kW, with or without batteries. Net metering covers renewable energy systems of up to 100 kW, with or without battery storage. (Department of Energy)
Contact Negros Power
034 705-6372 (034 705-NEPC); 09176837250; customercare@negrospower.ph; The Row, Lacson Street, Barangay Bata, Bacolod City.
Negros Power net metering FAQs
How long does Negros Power take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.
Sources
- Negros Power homepage — Negros Electric and Power Corporation (accessed October 27, 2026)
- MORE Power to simplify RE applications — Power Philippines (accessed October 27, 2026)