Subic EnerZone net metering: how to apply

Subic EnerZone Corporation. Subic EnerZone hasn’t published its own net-metering checklist online, so here are the national rules that apply and how to contact Subic EnerZone.

Checked October 27, 2026. Rules and fees change; confirm with Subic EnerZone before you apply.

At a glance

How to apply
Contact Subic EnerZone and ask for its net-metering desk.
ERC fee
—
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
20 working days once permits are in place (ERC); 10 working days during the energy emergency (DOE, April 2026)

What we found

  • We could not find a published net-metering process or an official website for Subic EnerZone.

How long it takes

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Rules Subic EnerZone must follow

Subic EnerZone net metering FAQs

How long does Subic EnerZone take to process net metering?
Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.