ZAMECO II net metering: how to apply

Zambales II Electric Cooperative. Here’s ZAMECO II’s net-metering process, documents and fees, from its own published guide.

Checked October 27, 2026. Rules and fees change; confirm with ZAMECO II before you apply.

At a glance

How to apply
Email all requirements to zameco2netmetering@gmail.com, with the letter of intent addressed to Engr. Romwil F. De Jesus.
ERC fee
₱1,500
Meter replacement
Capped at ₱3,000 for residential customers (ERC)
Processing time
Initial inspection 2 to 4 days after complete documents; bi-directional meter installed within 5 working days after the net-metering facility is complete.
ZAMECO II’s net-metering page

Steps to apply with ZAMECO II

  1. 1 Submit requirements Email the documents in the requirements list.
  2. 2 Account clearance ZAMECO II checks that your account is in good standing (bills paid before the due date).
  3. 3 Initial inspection ZAMECO II inspects your solar PV system and the metering facility you provide, 2 to 4 days after it receives complete documents.
  4. 4 Final inspection Call or text the office to schedule a final inspection of the metering facility.
  5. 5 ERC fee ZAMECO II collects ₱1,500 on behalf of the ERC, issues an acknowledgement receipt, and emails you a copy of the ERC official receipt.
  6. 6 Meter installation ZAMECO II installs the bi-directional meter within 5 working days after your net-metering facility is complete.

Requirements ZAMECO II lists

  • Letter of intent to join the net-metering program (addressed to Engr. Romwil F. De Jesus)
  • Copy of a government-issued ID
  • Single line diagram of the installed solar PV system, signed and sealed by a Professional Electrical Engineer
  • Certificate of Completion (Annex 2, JMC 001, s. 2026) from the municipal Building Official
  • ZAMECO II statement of account (electric bill)
  • Accomplished ERC Certificate of Compliance form for a Qualified End-User
  • Google Maps location (coordinates and map link)
  • Photos of the net-metering facility (meter base, disconnect switch, etc.)
  • Letter of authorization (template provided)
  • If needed: authorization letter and valid ID, notarized special power of attorney, contract of lease. If the account holder has died, the account name must be changed first.

The ERC’s September 2025 advisory says utilities may only require the application form, the CFEI from your LGU, the amended net-metering agreement and the ERC fee. If an item above isn’t on that list, ask ZAMECO II whether it’s still required.

Fees

FeeAmount
ERC Certificate of Compliance application fee (collected by ZAMECO II for the ERC)₱1,500

LGU permit fees (electrical permit, CFEI) are separate and vary by city or municipality.

How long it takes

ZAMECO II: Initial inspection 2 to 4 days after complete documents; bi-directional meter installed within 5 working days after the net-metering facility is complete.

  • 20 working days. Under the ERC’s 2025 amended rules, the utility has 20 working days to connect you once your permits are in place. (Ocampo & Suralvo Law Offices)
  • 10 working days during the energy emergency. In April 2026 the DOE directed utilities and cooperatives to finish processing within 10 working days while the national energy emergency (EO 110, s. 2026) is in force. Ask your utility whether this still applies. (GMA News)
  • Faster LGU permits. Under Joint Memorandum Circular No. 001, s. 2026, LGUs should issue the electrical permit within 3 working days and the CFEI within 7 working days, without extra requirements. (Department of the Interior and Local Government Region IV-A)

Good to know

  • This follows ZAMECO II's March 2026 application guide. An older version of the guide (September 2025) also listed a ₱168.00 inspection fee and a ₱500.00 notarial fee. The 2026 guide no longer lists them.
  • The ERC's 22 September 2025 advisory limits what utilities may require to an application form, the CFEI, the amended agreement and the COC fee. Ask ZAMECO II which items on its list are still required.

Contact ZAMECO II

zameco2netmetering@gmail.com; customersupport@zameco2.com; 047-602-2401 / 047-602-2402; National Highway, Nagbunga, Castillejos, Zambales.

ZAMECO II net metering FAQs

How much does net metering cost at ZAMECO II?
ZAMECO II lists: ERC Certificate of Compliance application fee (collected by ZAMECO II for the ERC) — ₱1,500. For residential customers, the meter replacement charge is capped at ₱3,000.
How long does ZAMECO II take to process net metering?
ZAMECO II says: Initial inspection 2 to 4 days after complete documents; bi-directional meter installed within 5 working days after the net-metering facility is complete. Under the ERC’s 2025 amended rules, utilities have 20 working days to connect you once permits are in place, and in April 2026 the DOE directed utilities to finish within 10 working days during the national energy emergency.
What documents does ZAMECO II ask for?
ZAMECO II lists 10 items, including letter of intent to join the net-metering program (addressed to engr. romwil f. de jesus) and copy of a government-issued id. The ERC’s September 2025 advisory limits required documents to the application form, the CFEI, the amended agreement and the ERC fee, so ask ZAMECO II which items are still needed.